Downtown has no room for more streetcars and buses. There is room underground, though. The North/South Line will make sure that Amsterdam becomes and stays more accessible. The subway line will transport 185,000 passengers per day quickly, safely, and comfortably through downtown Amsterdam. The ride from North to South now takes 31 minutes. The North/South Line will connect Amsterdam North with Amsterdam South. Travel time from Buikslotermeerplein to South Station is 16 minutes.

Vink Systemen supplies and installs ventilation ducts and Smoke Heat Evacuation (RWA) ducts in 8 metro stations. Special on this project are the oval RWA channels at De Pijp subway station.

Indicative work figures
23,000 m² of rectangular galvanized ductwork
2,900 m¹ round galvanized ductwork ≤ 315 mm
1,500 m² round galvanized ductwork > 315 mm
225 m² of fireproof insulation
3,500 m² of vapor-tight insulation
Installation of fire dampers, dampers, fans, grilles, etc.

RWA (Smoke Heat Drainage) ducts.
7,500 m² rectangular fire-resistant SHEV ductwork
400 m² round galvanized ductwork > 1,250 mm
2,700 m² round galvanized ductwork > 1,500 mm
320 m¹ oval ductwork finished in NCS color
Installation of fire dampers, dampers, fans, grilles, etc.

Details
Ductwork in special carts suitable for rail transport
Oval Smoke Heat Evacuation (RWA) ducts.

Project specifications

Location Amsterdam
Client VIA Noordzuidlijn (een handelsnaam van Visser & Smit Bouw bv)
Status Voltooid
Projectname North/South Line
Market segment Zorg & (Semi) overheid

    Check out our other projects

    RembrandtPark_RembrandtParkOne
    Amsterdam

    Rembrandt Park One


    The former building in Amsterdam West, known as “the Ringpark,” is undergoing a sustainable renovation and redevelopment. With which existing qualities are preserved and new ones added. For this redevelopment, Vink Systemen is providing the complete air technical installation. Under the new name “Rembrandt Park,” the complex should realize a great location for a mix between businesses and public facilities.
    Read more
    Hyde-Park
    Hoofddorp

    Hyde Park Hoofddorp


    Here the scope includes the supply and installation of the complete air technical installation. This includes supplying and assembling the air ducts, supplying the fittings including the air handling units, and engineering support in REVIT. Work is starting in the Nothing Hill block and here as many as 310 apartments will be fully completed. Together with our client P. van
    Read more
    Galapagos
    Leiden (Oegstgeest)

    Galapagos Leiden


    The office includes approximately 17,000 sq. ft. of office and laboratory space with parking and bicycle storage below. The office building was designed by OZ Architects and is characterized by a modern look, great transparency and flexible storey floors with extra free height. Commissioned by Schulte & Lestraden B.V., Vink Systemen is providing the complete air technology installation for this
    Read more
    Mall of the Netherlands
    Leidschendam

    Mall of the Netherlands


    By order of Roodenburg Installation Company, Vink Systemen BV supplied the complete air technical installation(s). Thus, through the entire mall, the main pipes were mounted. Here Vink Systemen installed the complete supply and return air through roof channels. This work took place both inside and on the roof. Westfield Mall Leidschenhage will from now on continue as Westfield Mall of
    Read more
    EDGE Amsterdam
    Amsterdam West

    EDGE Amsterdam


    EDGE Amsterdam West is a 48,000m² redevelopment of a 1970s office building. The building was designed by former de Architekten Cie architect, Oyevaar. Basisweg 10 is located in the transforming neighborhood of Amsterdam West, with APG and Alliander as main tenants. The building will be upgraded to an advanced and sustainable office building, meeting the highest standards of sustainability, technology
    Read more
    Tripolis Park Amsterdam
    Amsterdam Zuidas

    Tripolis Park Amsterdam


    During this project, Aldo van Eck’s monumental buildings will be revived. In addition, these buildings are going to be partially covered with a large glass facade. The glass facade will provide a completely new office building. This facade provides a connection of the old and new parts of Tripolis Park. And will make way for more than 30,000 square feet
    Read more
    The Accelerator Utrecht
    Utrecht Science Park

    The Accelerator Utrecht


    The innovation center will house growing, innovative companies working in life sciences and the health sector. The company will provide several functions. In addition to going to contain office, laboratory and parking spaces, it will also have an auditorium for 250 people, meet-and-greet facilities and general amenities such as a meeting center and expanded restaurant. Construction on the project recently
    Read more
    Biopartner Leiden
    Leiden

    Biopartner Leiden


    Biopartner provides office and laboratory facilities for companies doing research on vaccines and drugs in particular. The Biopartner Center in Leiden is closely tied to the growth of the Leiden Bio Science Park and is developing its fifth building, Biopartner 5, for the new campus in Oegstgeest. The construction of a fifth building is necessary as the four existing BioPartners
    Read more
    Kunstenpand Rotterdam
    Rotterdam

    Kunstenpand Rotterdam


    The “Heart of South” should provide a lasting physical and social impetus to Rotterdam South. The new building will house the Theater Zuidplein, a branch of the Rotterdam Library and will have various other cultural functions. A comprehensive program of arts, culture, reading and learning and social facilities ensure that the Arts Building will serve an important community function for
    Read more
    MECC Maastricht
    Maastricht

    MECC Maastricht


    Over the next few years, MECC Maastricht will be expanded and refurbished. By modernizing the convention center, MECC aims to host conferences of up to 5,000 visitors in the future. It is currently available for up to 3,000 people. There will also be more individual meeting spaces and the foyer will be taken care of. Watch an impression video here!
    Read more
    Rotterdam Ahoy Convention Centre (RACC)
    Rotterdam

    Rotterdam Ahoy Convention Centre (RACC)


    The RACC will open its doors in 2020. The convention center has 35 rooms and will feature the largest auditorium in the Netherlands and beautiful foyers and expo spaces. The RACC is suitable for large and smaller conferences. In addition, associated trade fairs may begin to take place. Images are from Urban Planning & Architecture Hart van Zuid area development
    Read more
    European Patent Office
    Rijswijk

    European Patent Office


    EPO grants patents to inventors, researchers and companies and is the second largest European organization, with multiple locations in Europe. Built on the lot of the existing building in Rijswijk, the new office offers 1,750 workstations and is over 100 meters tall. A special project for Vink Systemen in which the ducts and pipes for air distribution were integrated into
    Read more
    Distributiecentrum Jumbo
    Nieuwegein

    Jumbo distribution center


    The distribution center will have an important function in the supermarket chain’s growth ambitions. Going forward, the distribution center will ensure faster and more efficient delivery of so-called “slow move” items to the regional distribution centers and stores. Sustainability is at the heart of construction and is assessed using the BREEAM methodology. The project should be completed by mid-2019. Watch
    Read more
    Van Lent Amsterdam
    Amsterdam

    Van Lent Amsterdam


    Royal van Lent’s second yard should be completed in early 2019. The new shipyard, over 35 meters high, will soon be able to build superyachts as long as 160 meters. In addition to building new yachts, the hall is also used for refits of existing Feadship yachts. Commissioned by BRI Group, Vink Systemen BV supplies the complete air technical installation(s).
    Read more
    OK Centrum Flevoziekenhuis
    Almere

    OK Center Flevo Hospital


    For the purpose of this new OR center, Vink Systemen supplied and installed the air transport routes. All this in good consultation with the other construction parties, so that a cleanliness class H system could be delivered. Indicative work figures 2,000m² rectangular galvanized ductwork reindensity class H 600m¹ round galvanized ductwork cleanliness class H 200m² of vapor tight insulation Armaflex
    Read more
    Plukon in Wezep
    Wezep

    Plukon in Wezep


    Because the entire factory was covered in soot, no more food could be produced here. It was therefore decided to demolish the plant and replace it with a new production, storage and distribution center, which was completed in late April. Vink Systemen BV, together with other companies from the Vink Groep, has been closely involved in the realization of the
    Read more
    Renovatie Ahoy Rotterdam
    Rotterdam

    Renovation Ahoy Rotterdam


    Part of the transformation is the large-scale renovation of Ahoy, which includes the redevelopment of the five existing exhibition halls and hospitality outlets. The construction and installation work will be carried out by Ballast Nedam and Heijmans, which together form Hart van Zuid v.o.f. About seventy percent of the work has now been completed; the project will be completed in
    Read more
    Renovatie ministerie van VROM
    Den Haag

    Renovation Ministry of VROM


    The renovation of the 25-year-old building will create a new government office with 4,400 workstations. The latest technology is used for energy supply and climate control. Indicative work figures 22,500 m2 of galvanized ductwork 9000 m1 spiralo ductwork Details Supply, install and insulate air ducts Roof hoods and outdoor air vents supplied by Vink Systemen
    Read more
    Noord/Zuidlijn Amsterdam
    Amsterdam

    North/South Line Amsterdam


    Downtown has no room for more streetcars and buses. There is room underground, though. The North/South Line will make sure that Amsterdam becomes and stays more accessible. The subway line will transport 185,000 passengers per day quickly, safely, and comfortably through downtown Amsterdam. The ride from North to South now takes 31 minutes. The North/South Line will connect Amsterdam North
    Read more
    Image
    Amsterdam

    The Edge in Amsterdam


    The building will be named “The Edge. It has an impressive, open atrium and a unique shape. This building was the first in the Benelux to receive BREEAM Outstanding design certification and has now received the completion certificate for most sustainable office building in the world. Innovative practices and thoughtful solutions allowed the team to earn more and more credits.
    Read more
    Oceanco in Alblasserdam
    Alblasserdam

    Oceanco in Alblasserdam


    The shipbuilding hall has a gross floor area of 5,500 m², is 33m high, with a dry dock of 10m depth. In addition to the yacht building hall, the project includes 2,800 m² of offices and 13,000 m² of workshops, a canteen and other technical areas. The new shipyard will also include a spray shed of 2,800 square meters including
    Read more

    Are you running into something?

    We like to think with you!

    Get in touch